Place the first 10 foot long Guardian™ Gawk-Glare screen flush with the end of the concrete K-rail or Jersey Barrier and place the provided two each 1" diameter steel pipes through each top molded slots and into the pre-drilled holes of the barrier.
2.
As the holes in the concrete barrier may be filled with debris it may be necessary to lightly tap the top of the pipe.
3.
Place another Guardian™ Gawk-Glare screen on the adjacent barrier and slide toward the installed Guardian™ Gawk-Glare screen to interlock two extensions.
4.
Place steel pipes into each slot on the top and through the barriers as done previously.
5.
DO NOT Bolt the two Guardian™ Gawk-Glare screens together.
6.
Continue above process to complete installation.
7.
Contact Engineering Department for assistance or other methods of attachments.